Controversial Corrib gas will flow within weeks
The projected spend of €250m on the controversial project this year will lead to the overall costs exceeding €3.6bn. This is more than four times the original estimate of €800m for the project, which is 12 years behind its original projected completion time of 2003.
Áine Ryan: TUESDAY, 13 OCTOBER 2015
Penultimate permission granted by EPA
ALMOST two decades after its discovery, the Corrib Gas field has been given its penultimate permission, an industrial emissions licence, by the EPA (Environmental Protection Agency). The final statutory permission for the €3.6bn project is expected to be issued very soon by the Minister for Communications, Energy and Natural Resources, Alex White, clearing the way for the gas to flow from the Bellanaboy refinery.